Large-project rule watch › Idaho
Informational only, not legal advice. Summaries of official government sources as of the dates shown; they may be incomplete, out of date or wrong. Do not rely on them. Always check the issuing agency and its meeting agendas before acting.
4 cited records from official government sources (non-.gov sites are labeled). 3 of 3 listed places covered. Last checked 2026-11-27.
| Place | Coverage | Last checked | Note |
|---|---|---|---|
| Idaho | Covered | 2026-11-26 | State moratorium law (Idaho Code 67-6523) only. Counties and cities are listed separately. |
| City of Boise, Idaho | Covered | 2026-11-27 | Cited from cityofboise.org, the City of Boise's official website (not a .gov domain; labeled "Official city website"). Only the Nov. 6 proposal is cited. The adopted ordinance was not found on a city page, so the outcome is marked unconfirmed. |
| Kootenai County, Idaho | Covered | 2026-11-27 | Cited from kcgov.us, Kootenai County's official website (not a .gov domain; labeled "Official county website"). Ordinance 620 (Oct. 2025) and the Feb. 12, 2026 minutes are cited. |
"Not covered" means we have not cited this place from an official government source yet. It does not mean the place has no hearings, moratoria or rules.
Idaho Code 67-6523 lets a city or county adopt an emergency moratorium after a written finding of imminent peril. It can last no longer than 182 days, cannot run in consecutive periods, and needs a gap of at least one year before it is reinstated. To keep restrictions longer, the board must adopt an interim or regular ordinance with notice and a hearing.
A City of Boise news release dated November 6, 2026 says Mayor Lauren McLean proposed a moratorium on development of mega data centers within city limits, with a public hearing at the City Council meeting on Tuesday, November 10, and that if passed the moratorium would take effect immediately. The release says the city had no applications for mega data centers at that time. News reports (not used as citations) say the Council adopted a six-month emergency moratorium on November 10, but we did not find the adopted ordinance or an outcome statement on a city page. Verify the adopted ordinance, its definition of a large data center and its dates with the City of Boise before relying on this.
The Kootenai County Community Development meeting minutes of February 12, 2026 record a discussion item: after the Board approved the data center text amendment, staff asked whether to proceed with a draft ordinance that would prohibit all data centers. The minutes record commissioners' comments on the idea, including an option to keep data centers to micro size through the conditional use permit process, and a point that any ordinance should include a plan for building disposal. The minutes record no vote and no decision on a ban. We did not find a later adopted ban on the county site this pass.
Kootenai County Ordinance No. 620, adopted October 2, 2025 and published October 7, 2025, amends the county land use code for data centers. It expressly prohibits data centers in the Commercial zone and allows them in the Light Industrial and Industrial zones only with a conditional use permit. A new Kootenai County Code section 8.5.138 sets standards: a minimum parcel of ten acres, setbacks of at least 150 feet from parcels in the Agricultural, Agricultural Suburban, Restricted Residential, Rural and High Density Residential zones (and Commercial parcels with a residence), screening of mechanical equipment, and no data center over the Rathdrum Prairie Aquifer. The ordinance sets the standards and application requirements; check the county code for any later changes.
Covered with cited official records: Idaho; City of Boise, Idaho; Kootenai County, Idaho. Each place shows its own last-checked date.
Every listed place has cited records.
Pick Idaho in the free Large-project rule watch sign-up and confirm by email (double opt-in). Alerts are in test mode now, so no alert emails go out yet. Unsubscribe any time with one click.
No. It is informational only. Confirm every item with the issuing agency before acting.
JSON: GET /v1/rules?jurisdiction=id&rule_type=large_project (state-level records) or use a place id from /v1/jurisdictions.