The city's project page (updated November 10, 2026) says that at the October 30, 2026 City Council meeting the Special Use Permit requested for the Google data center project passed, along with a final plat, a development agreement, a decommissioning agreement and other associated items. It says the Planning & Zoning Commission voted on October 20 to recommend approval, and that on October 19 Google announced it was no longer seeking a tax abatement. The October 20 Planning & Zoning summary describes the request as a technology campus of about 1.66 million square feet with three data center buildings in the Business and Light Manufacturing (BLM) zoning district at Morris Thomas Road and Midway Road, built over six to eight years. See the city's project page for the agreement documents.

Key facts

Actionspecial use permit approved
Approved on2026-10-30
Project types
  • data_center
Zoning districtBLM (Business and Light Manufacturing)

Official source

Information Regarding Potential Google Data Center (project page, updated Nov. 10, 2026) · City of Hermantown, Minnesota (Official city website) · Project page updates (Oct. 19, Oct. 20 and Oct. 30, 2026)
Retrieved 2026-11-27 · last checked 2026-11-27 · topic: Where allowed