Local Rules API
Large-project rule watch › Minnesota
Informational only, not legal advice. Summaries of official government sources as of the dates shown; they may be incomplete, out of date or wrong. Do not rely on them. Always check the issuing agency and its meeting agendas before acting.
4 cited records from official government sources (non-.gov sites are labeled). 2 of 3 listed places covered. Last checked 2026-11-27.
| Place | Coverage | Last checked | Note |
|---|---|---|---|
| Minnesota | Covered | 2026-11-26 | State PUC solar and wind permitting only. Counties and cities are listed separately. |
| City of Hermantown, Minnesota | Covered | 2026-11-27 | Cited from hermantownmn.com, the City of Hermantown's official website (not a .gov domain; labeled "Official city website"). The adopted agreements themselves were not read; the city project page links them. |
| City of North Mankato, Minnesota | Not covered | 2026-11-26 | Not reviewed from an official .gov source yet. |
"Not covered" means we have not cited this place from an official government source yet. It does not mean the place has no hearings, moratoria or rules.
The Minnesota Public Utilities Commission permits solar electric generating facilities with a capacity of 50 megawatts or greater.
The Minnesota Public Utilities Commission permits wind energy projects of five megawatts or larger. For projects up to 25 MW, a county can issue the permit if it formally tells the PUC it will take on that authority, and counties may set stricter wind standards.
The City of Hermantown's Planning & Zoning Commission meeting summary of October 20, 2026 states that environmental review for the proposed data center campus was completed through an Alternative Urban Areawide Review (AUAR), adopted and approved by the City on October 5, 2026 under Resolution No. 2026-124, and that the final AUAR was submitted to the Minnesota Environmental Quality Board. The city's project page also reports that the City Council adopted the final AUAR at its October 5, 2026 meeting.
The city's project page (updated November 10, 2026) says that at the October 30, 2026 City Council meeting the Special Use Permit requested for the Google data center project passed, along with a final plat, a development agreement, a decommissioning agreement and other associated items. It says the Planning & Zoning Commission voted on October 20 to recommend approval, and that on October 19 Google announced it was no longer seeking a tax abatement. The October 20 Planning & Zoning summary describes the request as a technology campus of about 1.66 million square feet with three data center buildings in the Business and Light Manufacturing (BLM) zoning district at Morris Thomas Road and Midway Road, built over six to eight years. See the city's project page for the agreement documents.
Covered with cited official records: Minnesota; City of Hermantown, Minnesota. Each place shows its own last-checked date.
Not covered yet: City of North Mankato, Minnesota. "Not covered" does not mean there are no rules or hearings there.
Pick Minnesota in the free Large-project rule watch sign-up and confirm by email (double opt-in). Alerts are in test mode now, so no alert emails go out yet. Unsubscribe any time with one click.
No. It is informational only. Confirm every item with the issuing agency before acting.
JSON: GET /v1/rules?jurisdiction=mn&rule_type=large_project (state-level records) or use a place id from /v1/jurisdictions.